Milchplatz

Gravel works Milchplatz

The Challenge

In the course of the construction of a gravel works located to the Rhine directly several tunnels and silos made of HAMCO MultiPlate were used. Below the silo battery, consisting of twelve single silos, two conveyor belt tunnels connected by a pump sump made of corruga-ted steel parts were placed.

Twenty four factory-made funnels were integrated into these tunnel buildings. The third conveyor belt tunnel with three funnels was placed below a heap.
Five of the twelve silos have a big factory-made gate to have the option to take material from the silos by a wheel loader.

  • Profile Tunnel KR 20 / KR 23 / KR 28
  • Corrugation 200 mm x 55 mm
  • Span 2,99 m / 3,22 m / 3,59 m
  • Rise 2,99 m / 3,22 m / 3,59 m
  • Length 75,00 m / 125,00 m / 65,00 m
  • Plate thickness different plate thicknesses and types of bolting
  • Corrosion protection Hot-dip galvanization
  • Profile Silo 2 x SKR 118 / 10 x SKR 167
  • Corrugation 200 mm x 55 mm
  • Diameter 2 x 8,83 m / 10 x 12,50 m
  • Height 2 x 12,00 m / 10 x 12,00 m
  • Plate thickness different plate thicknesses and types of bolting
  • Corrosion protection Hot-dip galvanization